dc.description.abstractDelay in completion of construction projects is a worldwide issue with serious social and economic implications, inflicting significant financial losses to the involved parties. Consequently, disputes are generated and, therefore, costly and time-consuming judicial processes are invoked, which can be detrimental for the industry and the government. Especially for Cyprus, where its financial recovery is closely linked to the construction industry, and its burdened judicial system suffers to deliver justice on-time, delays have a significant impact. To effectively deal with this problem, one has to unveil its causes, and apply effective mitigation measures and practices. To date, the causes of delay in the Cypriot construction industry have yet to be determined using a consistent, scientific approach. The purpose of this thesis is to determine the most important causes of delay, and to detect the most applicable measures for delay mitigation, using a dataset derived from the construction industry of Cyprus. As a secondary objective, this thesis proposes a novel methodology for effective construction project control using state-of-the-art geospatial and ICT technologies. The determination of delay causes, and mitigation practices is carried out by means of an integrated statistical approach that considers the perception of the main stakeholders (i.e. owners, contractors and consultants) to identify commonly-accepted practices. Qualitative and quantitative data regarding the perception of professionals on the causes of delay and the optimal mitigation measures were collected via a voluntary sampling questionnaire process. The dataset was analyzed using an integrated statistical workflow that addressed the reliability of the sample, ranking of the most important delay causes and measures, and the determination of the perception of the involved parties via both non-parametric and parametric correlation tests. Concordantly, critical statistical indices were derived unveiling the significance of each delay cause and mitigation measure as perceived by each major stakeholder of the industry. The results illustrate that, although there is an a-priori disagreement in the perception of each stakeholder with respect to delay liability, commonly-accepted delay mitigation practices can be successfully identified and applied directly, promoting dispute avoidance.en_US
dc.formatpdfen_US
dc.language.isoenen_US
dc.publisherDepartment of Civil Engineering and Geomatics, Faculty of Engineering and Technology, Cyprus University of Technologyen_US
dc.rightsΑπαγορεύεται η δημοσίευση ή αναπαραγωγή, ηλεκτρονική ή άλλη χωρίς τη γραπτή συγκατάθεση του δημιουργού και κάτοχου των πνευματικών δικαιωμάτων.en_US
dc.subjectConstructionen_US
dc.subjectProject managementen_US
dc.subjectControlen_US
dc.subjectDelayen_US
dc.subjectCausesen_US
dc.subjectMeasuresen_US
dc.titleThe risk of delay in Cyprus construction industry : causes, effects and controlen_US
dc.typePhD Thesisen_US
dc.affiliationCyprus University of Technologyen_US
dc.description.membersVassilis Gikas, Evangelos Akylasen_US
dc.relation.deptDepartment of Civil Engineering and Geomaticsen_US
dc.description.statusCompleteden_US
cut.common.academicyear2017-2018en_US
dc.relation.facultyFaculty of Engineering and Technologyen_US
item.fulltextWith Fulltext-
item.languageiso639-1en-
item.grantfulltextopen-
item.openairecristypehttp://purl.org/coar/resource_type/c_db06-
item.cerifentitytypePublications-
item.openairetypedoctoralThesis-
crisitem.author.deptDepartment of Civil Engineering and Geomatics-
crisitem.author.deptDepartment of Civil Engineering and Geomatics-
crisitem.author.deptDepartment of Civil Engineering and Geomatics-
crisitem.author.facultyFaculty of Engineering and Technology-
crisitem.author.facultyFaculty of Engineering and Technology-
crisitem.author.facultyFaculty of Engineering and Technology-
crisitem.author.orcid0000-0003-4483-806X-
crisitem.author.orcid0000-0002-0248-1085-
crisitem.author.orcid0000-0002-2684-547X-
crisitem.author.parentorgFaculty of Engineering and Technology-
crisitem.author.parentorgFaculty of Engineering and Technology-
crisitem.author.parentorgFaculty of Engineering and Technology-
Appears in Collections:Διδακτορικές Διατριβές/ PhD Theses
Files in This Item:
File Description SizeFormat
PhD_Vacanas Yiannis_Abstract.pdfAbstract8.19 kBAdobe PDFView/Open
PhD_Vacanas Yiannis_2018_v14.pdfFull text5.34 MBAdobe PDFView/Open
CORE Recommender
Show simple item record

Page view(s) 5

695
Last Week
0
Last month
34
checked on Mar 14, 2025

Download(s) 5

568
checked on Mar 14, 2025

Google ScholarTM

Check


Items in KTISIS are protected by copyright, with all rights reserved, unless otherwise indicated.