  4. The risk of delay in Cyprus construction industry : causes, effects and control
  • Details

The risk of delay in Cyprus construction industry : causes, effects and control

Date Issued
November 2018
Author(s)
Vacanas, Yiannis  
Advisor
Danezis, Chris  
Hadjimitsis, Diofantos G.  
Abstract
Delay in completion of construction projects is a worldwide issue with serious social
and economic implications, inflicting significant financial losses to the involved parties.
Consequently, disputes are generated and, therefore, costly and time-consuming judicial
processes are invoked, which can be detrimental for the industry and the government.
Especially for Cyprus, where its financial recovery is closely linked to the construction
industry, and its burdened judicial system suffers to deliver justice on-time, delays have
a significant impact. To effectively deal with this problem, one has to unveil its causes,
and apply effective mitigation measures and practices. To date, the causes of delay in
the Cypriot construction industry have yet to be determined using a consistent, scientific
approach. The purpose of this thesis is to determine the most important causes of delay,
and to detect the most applicable measures for delay mitigation, using a dataset derived
from the construction industry of Cyprus. As a secondary objective, this thesis proposes
a novel methodology for effective construction project control using state-of-the-art
geospatial and ICT technologies. The determination of delay causes, and mitigation
practices is carried out by means of an integrated statistical approach that considers the
perception of the main stakeholders (i.e. owners, contractors and consultants) to identify
commonly-accepted practices. Qualitative and quantitative data regarding the
perception of professionals on the causes of delay and the optimal mitigation measures
were collected via a voluntary sampling questionnaire process. The dataset was
analyzed using an integrated statistical workflow that addressed the reliability of the
sample, ranking of the most important delay causes and measures, and the determination
of the perception of the involved parties via both non-parametric and parametric
correlation tests. Concordantly, critical statistical indices were derived unveiling the
significance of each delay cause and mitigation measure as perceived by each major
stakeholder of the industry. The results illustrate that, although there is an a-priori
disagreement in the perception of each stakeholder with respect to delay liability,
commonly-accepted delay mitigation practices can be successfully identified and
applied directly, promoting dispute avoidance.
Subjects

Construction

Project management

Control

Delay

Causes

Measures

File(s)
Thumbnail Image
Name

PhD_Vacanas Yiannis_Abstract.pdf

Size

8.19 KB

Format

Adobe PDF

Checksum (MD5)

a3b4841959b40f64379209785669bfe9

Thumbnail Image
Name

PhD_Vacanas Yiannis_2018_v14.pdf

Size

5.22 MB

Format

Adobe PDF

Checksum (MD5)

1a41ab4c5bd3a74991d8887fa60b1568

Explore by
  • Collections
  • Research Outputs
  • Researchers
  • Faculty & Departments
  • Theses
  • Patents
  • Projects
  • Journals
  • Conferences
Useful Links
  • Researcher Portfolio Guide
  • Researcher Profile
  • Create an ORCID ID
  • CUT Open Access Author Fund
  • ETDS Guide
Copyright Policies

Use Sherpa/Romeo to find publisher copyright policies

Go
Go
  • SPARC Author Addendum Engine
  • National Open Access Policy in Cyprus
Deposit your work to Ktisis
  • Self-archiving. Please sign in to Ktisis.
  • Email your work to:
    library.dspace@cut.ac.cy
  • Contact your subject librarian

Member of

OpenAIREre3dataOpenDOARCOREDART
Cyprus University of Technology
Library and
Information
Services

Copyright © 2022 - Library and Information Services Feedback - Built with DSpace-CRIS - 4Science

  • Accessibility settings
  • Privacy policy
  • End User Agreement
COAR NotifyCOAR Notify